Drawing status codes and revision codes on UK projects

What S0 to S5, A, P01 and C01 mean under the UK National Annex to BS EN ISO 19650-2, what changed in 2021, why B codes are deprecated and what you can build from on site.

Reviewed against UK BIM Framework guidance on the UK National Annex (2021) to BS EN ISO 19650-2. Updated November 2026.

Every drawing that reaches site carries two answers in its title block. Which issue is this? And what is it for? The first is the revision code. The second is the status code. Get either wrong and someone builds to the wrong sheet, or builds to the right sheet before it was meant to be built from.

This page explains both as they're set out in the UK National Annex to BS EN ISO 19650-2, the standard UK projects use when they work to ISO 19650. Your project's own information standard has the final say. It's the document that tells you what each code means on that job and it can add to what's here.

The short version

  • P revisions (P01, P02, P03) are preliminary. They're shared for coordination, information, comment or approval. They aren't contractual.
  • C revisions (C01, C02) are contractual. A C revision is information that has been authorised and accepted and published.
  • S0 means work in progress inside the team producing the sheet. It isn't shared.
  • S1 to S5 are the shared codes. They say why a preliminary sheet has been shared: coordination, information, comment, authorisation or acceptance. None of them is for building from.
  • A status codes say a sheet has been authorised and accepted. What each A number means (construction, for example) is set by the project, not the standard. No A number means construction on every project.
  • B status codes are deprecated in the 2021 annex, which strongly advises against using them. If a legacy project uses one, its information standard decides what it means.
  • A later issue replaces the one you build from only when it's published for that use. The earlier issue isn't deleted. It stays on the record with its history.

Status codes at a glance

None of S0 to S5 is for building from.

CodeMeaningPermitted use
S0Work in progressNot shared
S1Suitable for coordinationCoordination only
S2Suitable for informationInformation only
S3Suitable for review and commentReview and comment only
S4Suitable for review and authorisationAuthorisation by the lead appointed party
S5Suitable for review and acceptanceAcceptance by the client
A1, A2, A3 and onAuthorised and acceptedSet by your project's information standard; one is usually for construction
B1, B2 and onDeprecated in 2021: partially authorised or accepted, with commentsDeprecated: avoid; check the legacy project's rules

Print it for the site cabin: the free one-page chart of UK drawing status and revision codes (PDF). No sign-up.

Revision codes: P and C

The UK National Annex uses a letter and two digits.

CodeMeaningWhere you'll see it
P01.01, P01.02Work in progress versions inside the team producing the drawingTheir own work area. You shouldn't normally receive these.
P01, P02, P03Preliminary revisions, shared with other teamsCoordination, information, review and comment, approval
C01, C02Contractual revisions, authorised and acceptedPublished information, the issue the contract relies on

The C stands for contractual. It's often said to mean "construction" or "complete", and that's worth correcting, because a C revision isn't automatically a construction issue. What it's suitable for is in the status code beside it.

The work in progress suffix uses two digits after a full stop (P01.01, not P01.1). It drops away when the drawing is shared, so the first shared issue is simply P01.

Status codes: what the sheet is for

The status code (many people still call it suitability, which was the BS 1192 term) says what a sheet may be used for. S0 is work in progress that hasn't left the team producing it; S1 to S5 say why it has been shared; A codes say it has been published. These are the codes in the 2021 version of the UK National Annex.

CodeMeaningWhat it means on site
S0Initial status: work in progress inside the team producing itYou shouldn't have it. Ask where it came from.
S1Suitable for coordinationShared so other designers can coordinate with it. Not for building from.
S2Suitable for informationShared so you know what's coming. Not for building from.
S3Suitable for review and commentShared for your comments. Not for building from.
S4Suitable for review and authorisationShared so the lead appointed party can authorise it before it goes to the client. Not for building from yet.
S5Suitable for review and acceptanceShared so the client (the appointing party) can review and accept it. Not for building from yet.
A1, A2, A3 and onAuthorised and acceptedPublished, with a C revision. The project's information standard says what each A number means. One of them is usually the issue for construction, but no A number means construction on every project.
B1, B2 and onDeprecated in 2021: partially authorised or accepted, with commentsThe 2021 annex strongly advises against using B codes. If one appears on a legacy project, check its information standard before using the sheet.

S1 to S5 travel with a P revision. The A codes travel with a C revision. If you see an A status on a P revision, or a C revision with an S status, query it before using the sheet.

The plain rule for site is this. Build from information published with the A code your project's information standard sets for construction. If the status code, the transmittal and an instruction you've been given don't agree, resolve it through the project's authorised process before building. A status code says what a sheet may be used for; it isn't an instruction to change the work. An S2 sheet that "everyone knows is right" is still a sheet issued for information.

What changed between P01 and P02?

Both issues show the same ground floor. Slide across the drawing to see where the wall, door and drain moved on P02.

REVISION STUDY / 001Try the example
P01 · EarlierP02 · Revised

The internal wall shifts into the adjoining room.

Does the revised layout affect setting out or the room fit-out?

Illustrative example — not a project drawing or live AI result.
Compare your own two revisions

Common questions about single codes

What does S2 mean on a drawing?

Suitable for information. The sheet has been shared so you can see what's coming. It travels with a P revision and it isn't for building from, however close to final it looks.

Can you build from S4?

No. S4 means suitable for review and authorisation: the sheet is waiting for the lead appointed party to authorise it. Under the 2018 annex S4 meant suitable for stage approval, which is why people still argue about it. Neither meaning lets you build from it.

What does C01 mean?

The first contractual revision. The sheet has been authorised, accepted and published. C means contractual, not construction: check the A code beside it to see what it's suitable for.

What replaced S6 and S7?

Nothing one for one. The 2021 annex withdrew both, along with CR. In practice, information for the project and asset information models now goes through the same S4 (authorisation) and S5 (acceptance) steps as everything else, and the project's information standard says which A code marks the result.

What does B1 mean?

B1 meant partial authorisation or acceptance with comments under the 2018 annex. B codes are deprecated in the 2021 annex, which strongly advises against using them. If one appears on a legacy project, check its information standard before you use the sheet.

What changed in 2021

The UK National Annex was revised in February 2021. The standard itself didn't change; BS EN ISO 19650-2:2018 is still the current edition. But the annex changed several status codes and it's why two people on the same job can read S4 differently.

Code2018 annex2021 annex
S4Suitable for stage approvalSuitable for review and authorisation
S5Withdrawn, not usedSuitable for review and acceptance
S6Suitable for PIM authorisationWithdrawn
S7Suitable for AIM authorisationWithdrawn
B codesPartial authorisation or acceptance with commentsDeprecated: strongly advised not to use
A codesAuthorised and accepted, with each A number tied to a project stageAuthorised and accepted, with each number's meaning set by the project's information standard
CRAs-constructed recordWithdrawn. The project defines an A code for it instead.

If your appointment documents were written against the 2018 annex, the 2018 meanings are likely to apply on that job, and older projects often were. Your appointment and the project's information standard decide. It's worth checking which annex your project's information standard refers to before you argue about an S4.

Why people still say BS 1192

BS 1192:2007+A2:2016 and PAS 1192-2:2013 were the British documents for producing and sharing construction information. Both were withdrawn in January 2019, when BS EN ISO 19650-1 and BS EN ISO 19650-2 were published in the UK with the UK National Annex.

A lot of the vocabulary carried over, including the idea of a common data environment, file naming fields and suitability codes. So "BS 1192 naming" and "BS 1192 codes" are still how many people describe them, and plenty of templates still have BS 1192 in the footer. It doesn't matter much in conversation. It matters when you're relying on what a code means, because the meaning comes from whichever document your project actually adopted.

ISO 19650-2 is being revised and the draft also replaces Part 3. It hasn't been published: in August 2026 ISO recorded a decision to hold a second draft ballot. Until a new edition is out, the current ones stay in force (Parts 1 and 2 from 2018, Part 3 from 2020). Expect this page to change when it is.

What superseded means in practice

Superseded means replaced for a particular use. When C02 of a sheet is published for construction, C01 stops being the issue to build from. But a later issue that's only shared, say P04 at S3 for comment, doesn't replace the C01 the site is building from, even though it's the latest thing you've received. Keep the two apart: the latest issue received and the current issue authorised for construction. Record the date each replacement took effect.

The earlier issue isn't deleted. A common data environment keeps it with its history: who issued it, when and for what. That record, which is what the archive state is for, is how you show what was current on a given date. It doesn't have to mean a separate archive folder.

On site, superseded needs more than a status in the system. In practice:

  • Take superseded prints out of the site office, the welfare cabins and the work face, or mark them clearly as superseded.
  • Update the drawing register so the current issue for construction is the one people look up.
  • Tell anyone who set out, ordered or fabricated from the earlier issue. They're the ones a revision costs.
  • Keep a copy of the superseded sheet with the date you stopped using it. If a dispute comes later, you'll need to show what you built from and when it changed.

The drawing register

A drawing register is the list of every drawing on the job and its current issue. It's how anyone on site can check, in seconds, whether the sheet in their hand is the one to use.

As a minimum, it should show the drawing number, title, current revision, status code, date of issue, who issued it and where it was distributed (often by transmittal reference). A register that keeps the latest issue received apart from the current issue authorised for construction, and lists earlier revisions with the date each was superseded, answers the question that comes up in every dispute: what was current on that date?

A transmittal is the record that goes with an issue. It says which drawings, at which revision and status, went to whom and when. If a revision arrives without one, ask for it. It's your evidence of when you received the change.

One drawing's life, start to finish

This is an illustrative example. Here the project's information standard uses A4 for construction; yours may use a different A number, and its codes for each step may differ.

IssueStatusWhat's happening
P01.01, P01.02S0The designer is working on the sheet. Nobody outside their team sees it.
P01S2Shared with the contractor for information, so they can see what's coming.
P02S3Revised after coordination and shared for review and comment. The contractor comments on buildability.
P03S4Comments addressed. Shared for authorisation by the lead appointed party.
P03S5Authorised, and shared with the client for review and acceptance.
C01A4 (construction, in this example only)Authorised, accepted and published. This is the issue the site builds from.
P04S3A proposed change, shared for comment. It's the latest issue received, but C01 is still the issue for construction.
C02A4 (construction, in this example only)The change authorised, accepted and published. C01 is superseded for construction. Someone needs to check what was already built or ordered to C01.

The step that goes wrong is the last one. A new C revision arrives, gets filed and nobody compares it properly with the one the site has been working from. That's what the revision review checklist is for.

Then check what the change does to the quantities. If C02 moves a wall or adds a door, the order placed against C01 is wrong. A comparison shows you the change but doesn't measure it. Quantity Take-off, a free tool from PlanOps, counts the tagged items on the new sheet and marks each one on the drawing, so you can set them against what was ordered.

Sources

Reviewed against UK BIM Framework guidance on the 2021 National Annex (Guidance Part 2, edition 6, section 3.1.10). The National Annex itself is published by BSI and isn't free. If your project relies on a code's exact wording, read it in the annex your appointment names. Last checked 5 November 2026.